Dynamics User Group

Since 1995 - The Microsoft Dynamics Online User Community

Advance payment to supplier

Last post 08-14-2008 3:24 by kiLL6. 11 replies.
Page 1 of 1 (12 items)
Write a New Post Sort Posts: Previous Next
  • 08-08-2008 4:46

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Advance payment to supplier

    Hi
      
        Is there a way in nav to linked the payment of diff vendor into one Vendor.

    This is scenario:

      We create a PO for vendor(abc) then that will be pay the charges in advance, but to diff supplier vendor(ex. Bureau of Custom). Is there a way to do that in nav. or do you encountered that scenario...hoping for your Reply. :D

     

    • Post Points: 20
  • 08-08-2008 14:52 In reply to

    • Romeo
    • Top 75 Contributor
      Male
    • Joined on 12-19-2007
    • Lebanon
    • Posts 239
    • Points 10,390

    Re: Advance payment to supplier

    Answer

    you mean setting vendor ABC in the PO as buy from vendor in PO header

    and Bureau of Custom as  pay to vendor will not solve the problem?

    Romeo

    • Post Points: 70
  • 08-09-2008 4:34 In reply to

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Re: Advance payment to supplier

    Answer

    Hi

    We pay the PO in installment payment..Exmple

    First payment is vendor(A)
    Second payment is vendor(B)
    Third payment is vendor(C)

    This payment is particular or related to that PO.

    • Post Points: 20
  • 08-11-2008 10:44 In reply to

    • Romeo
    • Top 75 Contributor
      Male
    • Joined on 12-19-2007
    • Lebanon
    • Posts 239
    • Points 10,390

    Re: Advance payment to supplier

    Answer

    i'm not sure what is exactly your case but what i usually do is the following:

    Create Purchase order for items

    create separate purchase orders from different vendors for custom duties, freight,...

    the regular case, is post receive the purchase order, then assign each of the "charge item" PO's to that order.

    in some cases customers pay these charges before receiving the products, and they want to link these charges to PO without assignment. i create a dimension called "purchase order" containing the order number and i assign it to the PO all related "Prepaid" charges.

    in some cases we make a customization depending on the customer's needs

     

    hope this helps :)

    Romeo

    • Post Points: 70
  • 08-11-2008 13:05 In reply to

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Re: Advance payment to supplier

    Answer

    Thanks ROMEO..I thinks this is the solution im looking for...but still have one question...Is that Charge item will be part of the COST of the origianl PO?hoping for your reply..thanksSmile

    • Post Points: 20
  • 08-11-2008 14:30 In reply to

    • Romeo
    • Top 75 Contributor
      Male
    • Joined on 12-19-2007
    • Lebanon
    • Posts 239
    • Points 10,390

    Re: Advance payment to supplier

    Answer

    once assigned to the purchase receipt entries of the PO, yes, the item cost will be purchase price + all assigned costs

    Romeo

    • Post Points: 70
  • 08-12-2008 3:39 In reply to

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Re: Advance payment to supplier

    Answer

    ah....Thank you very much....for the support..TYSmile

    • Post Points: 5
  • 08-12-2008 4:51 In reply to

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Re: Advance payment to supplier

    Answer

    Hi again, I have another question, we have different Account for Inventory and COGS, if I will post an charge item and I have diff. inventory per item..in one PO

    what will be the Entry for that..I was wondering if will go equally to the inventory account of the Item?hoping for your reply....ty

     

    • Post Points: 20
  • 08-12-2008 8:42 In reply to

    • Romeo
    • Top 75 Contributor
      Male
    • Joined on 12-19-2007
    • Lebanon
    • Posts 239
    • Points 10,390

    Re: Advance payment to supplier

    it will take the COGS & direct cost applied account from the setup of product posting group of the charge item,

    the inventory account will be the one used for items. (inventory posting group-Location)

    Romeo

    • Post Points: 70
  • 08-12-2008 8:56 In reply to

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Re: Advance payment to supplier

    We have diff. inventory and Cogs account per Item category, It means we will create diff. charge item for each per item Category? Is my understanding correct?hoping for your reply...ty

    • Post Points: 20
  • 08-12-2008 13:53 In reply to

    • Romeo
    • Top 75 Contributor
      Male
    • Joined on 12-19-2007
    • Lebanon
    • Posts 239
    • Points 10,390

    Re: Advance payment to supplier

    in your case yes.

    when making the setup, i usually use the same account for all item categories, and create a dimension called "item category" and use dimension values to get detailed information per categorie.

    Romeo

    • Post Points: 70
  • 08-14-2008 3:24 In reply to

    • kiLL6
    • Top 150 Contributor
    • Joined on 11-13-2007
    • Posts 132
    • Points 2,420

    Re: Advance payment to supplier

    Answer

    Thanks..for your Advise...I really appreciate it...TYSmile